What is the estimated final cost of building the Medupi Power station after all six boilers will have come into operation and when will the first boiler and all boilers come into operation

Skip Navigation LinksHome > Parliamentary Updates > What is the estimated final cost of building the Medupi Power station after all six boilers will have come into operation and when will the first boiler and all boilers come into operation
What is the estimated final cost of building the Medupi Power station after all six boilers will have come into operation and when will the first boiler and all boilers come into operation
31/08/2012

Question for written reply

Question no.: 2252

Date of publication: September 2012

2252. Mr L W Greyling (ID) to ask the Minister of Public Enterprises:
(a) What is the estimated final cost of building the Medupi Power station after all six boilers will have come into operation and (b) when will (i) the first boiler and (ii) all boilers come into operation?    NW2830E

Reply:
(a) The current cost to complete the Medupi Power Station is estimated at R98.9 billion excluding interest during construction, but including escalation and transmission integration costs. 

(b)(i) In the second half of 2013. 

(b)(ii) In 2017.